1.0 Business discussion, cooperation exchanges 1.1 Party A provides detailed documents of the project 1.2 Theme exploration, we submit the artwork display proposal and sketch of the style
2.0 Evaluation by Party A 2.1 We draw up the engineering budget 2.2 Party A approves the project budget, and two parties sign the contract
3.0 After signing the contract, Party A should pay the deposit within 3 days 3.1 We collect and study the documents and data, then improve the artwork design solution 3.2 Confirmation by Party A 3.3 Implement the confirmed solution and start production 3.4 Party A makes the progress payment 5 days before installation 3.5 Installation setting
4.0 Transfer 4.1 Acceptance check by Party A within 3 days 4.2 The balance should be paid within 7 days after acceptance 4.3 OK,happy ending